In most many small companies, the procedures for handling extra work is not very well established. In order to make sure that everyone on the jobsite complies with the paperwork for extra work is to implement an extra work ticketing system. This means, whenever an extra work will be performed, it must go through the […]
In schedules, when showing drywall installation, it is a common mistake to show it as a single item. What precedes drywall are the following: Stud framing, Installation of risers, pipes and conduits, backing or blocking, insulation material. There is an important point however. The drywall does not finish before those pipes and conduits and insulation […]