Construction and Civil Engineering News and Knowledge

Pour Strips

Concrete Pour Strips: Purpose, Design, and Construction Considerations

During the construction of large concrete slabs, engineers sometimes intentionally leave a narrow section unpoured. Known as a pour strip or closure strip, this temporary opening allows the surrounding concrete to undergo most of its early shrinkage before the remaining section is cast. Once the strip is filled, the slab becomes structurally continuous with lower restraint stresses and a reduced risk of shrinkage-related cracking.

Why Are Pour Strips Used?

Concrete naturally shrinks as it cures and also expands and contracts with temperature. In large slabs restrained by columns, walls, or foundations, these movements can generate tensile stresses that increase the likelihood of cracking. Delaying the closure pour allows much of the early shrinkage to occur before the slab is made continuous, significantly reducing restraint stresses.

In post-tensioned (PT) slabs, pour strips often serve an additional purpose. Besides accommodating shrinkage, they provide access for hydraulic jacks used to stress tendons at intermediate anchors. The closure strip is typically cast only after the tendons on both sides have been stressed.

Typical Applications

Pour strips are commonly used in:

  • Large suspended floor slabs
  • Post-tensioned slabs
  • Podium decks
  • Parking structures
  • Bridge decks
  • Industrial floors
  • Large mat foundations

They are particularly beneficial in long, highly restrained concrete elements where shrinkage stresses can become significant.

Size and Timing

Pour strips are typically 600 to 1,500 mm (2 to 5 ft) wide, although the required width is determined by the structural engineer.

The closure pour is commonly delayed 28 to 56 days to allow most early shrinkage to occur. However, the waiting period depends on the structural design, concrete properties, environmental conditions, and construction schedule.

In some projects, engineers approve earlier closure—sometimes after only 14 days—by specifying shrinkage-reducing admixtures (SRAs), high-early-strength concrete, or other engineered solutions.

Construction Challenges

Although pour strips improve long-term structural performance, they also introduce practical construction challenges.

The open strip interrupts the working deck, creating a trip hazard and making it more difficult for workers and equipment to move across the slab. Contractors often install temporary plywood covers, protect exposed reinforcing steel from damage, and remove any rainwater that collects in the opening before the closure pour.

Pour strips also affect construction sequencing. Because the slab remains incomplete, adjacent shoring and backshoring often cannot be removed until the closure strip reaches its required design strength. This may delay follow-on trades and extend the project’s critical path.

To reduce these schedule impacts, some modern post-tensioned systems use mechanical lockable dowel systems or other engineered details that eliminate the need for traditional open pour strips in certain applications. However, the advantages and disadvantages of these alternatives should be evaluated on a project-specific basis.

Surface Preparation and Closure Pour

Proper preparation of the existing concrete is essential for a durable closure pour.

The concrete surface should be roughened by removing laitance, cleaned of dirt and form-release agents, and brought to a saturated surface-dry (SSD) condition. Exposed reinforcing steel should also be cleaned, particularly at lap splice locations.

The closure concrete must then be properly placed, consolidated, vibrated, cured, and finished according to the project specifications. Poor surface preparation or inadequate workmanship can create a weak cold joint that reduces durability and may allow water infiltration.

Many projects specify non-shrink concrete or shrinkage-compensating materials for the closure pour to further minimize shrinkage within the strip itself.

Pour Strip vs. Expansion Joint

Pour strips and expansion joints serve very different purposes.

​In a pour strip, reinforcement is detailed to provide full structural continuity after the closure pour. The standard practice uses projecting starter bars extending into the strip from each adjacent slab section. During the curing phase, these bars remain disconnected or unrestrained, allowing the surrounding concrete to undergo early drying shrinkage freely without developing restraint stresses. Once the shrinkage period is complete, the bars are lap-spliced or mechanically connected, and the closure concrete is poured to embed the steel—turning the separate slabs into a single, continuous structural element.

An expansion joint, by contrast, is a permanent separation that accommodates movement caused by temperature changes, shrinkage, creep, and other long-term effects. Reinforcing steel generally does not continue uninterrupted across an expansion joint. Where load transfer is required, engineers typically use smooth dowels or similar devices that permit movement while transferring shear forces.

Key Takeaway

A pour strip is a proven construction technique that helps reduce shrinkage-induced stresses while accommodating construction sequencing requirements. When properly designed, detailed, and constructed, it minimizes the risk of cracking, improves long-term durability, and restores structural continuity after the closure pour. Although pour strips introduce temporary scheduling and logistical challenges, they remain an important tool in the construction of large reinforced and post-tensioned concrete structures.

PostBy: A. Tuter


Terms of Use: Unauthorized copying is prohibited; we maintain dated records to document original publication. Content may contain inaccuracies. See our Terms Page.